I will take Jamaicans on a short history of this 360 MW Project, enjoy.
- March 25, 2008 the OUR issues a Request for Proposal to build a 480 MW power plant on a build own and operate (BOO) basis. See attached document here renewables_rfp_ver_11.
- April 29, 2011 the OUR advices that JPS won the bid to provide 480MW of base load and was the sole bidder. See attached document here JPS WINS BID
- April 12, 2011 OUR issued an amended document , which provided an extension to the deadline relating to the project. See amended document here supply_of_up_to_480mw__base_load_generating_capacity_on_boo_addendum_3_apr_12_2011_0
- Dec 9, 2011 the OUR announces that JPS has been given the green light to build this 480MW power plant. See link http://jis.gov.jm/jps-to-build-360mw-modern-plant/
- After missing a number of deadlines for fuel sourcing agreement, by JPS, OUR terminates the process . See attached document media_release_-_our_terminates_jps_360mw_rfp_process
- August 5, 2013 OUR issues a long statement on the botched procurement process. http://www.our.org.jm/ourweb/our-statement-procurement-additional-base-load-capacity
- August 8, 2013 OUR announces its has received 5 bids for the 360Mw base load generating capacity, see link here http://www.our.org.jm/ourweb/our-opens-bids-proposals-generation-capacity
I will now turn over the next sequence of events to the Gleaner, who has done a very good job here.
http://digjamaica.com/blog/2014/05/06/unravelled-tracking-the-controversial-ewi-international-deal/
Lots of reading but its worth it.